# Is there a way to get the current viewport (date/time range) of a scheduling gantt chart?

**URL:** <https://community.palantir.com/t/is-there-a-way-to-get-the-current-viewport-date-time-range-of-a-scheduling-gantt-chart/6397>\
**Category:** Ask the Community\
**Tags:** workshop, dynamic-scheduling\
**Created:** [April 13, 2026, 11:33am UTC](https://community.palantir.com/t/is-there-a-way-to-get-the-current-viewport-date-time-range-of-a-scheduling-gantt-chart/6397 "2026-04-13T11:33:53Z")\
**Posts on this page:** 1\
**Page:** 1

<div class="post-metadata">

**Author:** ![djpoulsen21](https://yyz1.discourse-cdn.com/palantir/user_avatar/community.palantir.com/djpoulsen21/32/6331_2.png) [@djpoulsen21](https://community.palantir.com/u/djpoulsen21)\
**Post date:** [April 13, 2026, 11:33am UTC](https://community.palantir.com/t/is-there-a-way-to-get-the-current-viewport-date-time-range-of-a-scheduling-gantt-chart/6397/1 "2026-04-13T11:33:53Z")

</div>

I have a workshop with two scheduling gantt charts, and I am trying to sync the view when a user scrolls on one of them. Both charts use the same variables for the timeline start and end timestamps as well as the custom display range start/end timestamps.

Looking for a way to sync the views when the user scrolls on one chart.

I tried to use a right-click on the the resource row to capture the date/time of the click, but the Selected Start Date workshop variable only seems to be available on actions (not events). If I could save the date/time into a variable on a right-click, I could get the two charts to sync.

Better yet, if I could somehow retrieve the dates from the header… e.g. -

 ![image](https://canada1.discourse-cdn.com/palantir/original/2X/e/e43b8125fc9cb96d5669e5e60684358b5dad44ba.png)

Are those stored/accessible?