[Scheduling Gantt Chart widget] Drag Cursor to Create Action

Hi, all.
I would like to ask about the Scheduling Gantt Chart widget

I would like to implement a function using “Drag Cursor to Create Action”.
“Drag Cursor to Create Action” can display an action form, but can it display a workshop overlay?

As for user interaction, when the “Drag Cursor to Create Action” is executed, another “Schedule Gantt Chart Widget” widget will display so that the user can view it while executing the action.

Hi Tozuka!

Unfortunately, the “Drag Cursor to Create Action” feature doesn’t support triggering Workshop events such as opening an overlay. Currently that can only be done via Right Click Actions, On Row Select Event, or On Puck Select Event.

We do support bi-directional updates between to Scheduling Gantt Charts. If you are using Scenarios, there is an toggle for “Load Data From Scenario.” Here you would select the Output Scenario variable from the related chart chart (See example below). This should happen automatically if you are not using Scenarios.

Scenario Configuration Chart 1

Scenario Configuration Chart 2

Summary